Overhaul, cleaning, and reassembly
(Example) Model: FM30 · Thermal conductivity area 277 m2
Before starting work
The total required time is about 12 hours.
The required number of people for this assignment is 6.
Please refer to the table below for the number of personnel involved in each task.
Essential tools and materials: ratchet wrench, hose, wiping material, brush, grease, steel tape measure (over 2 meters)
Before starting the homework, check item ll: 1. Whether the liquid is completely discharged. Are all pressure gauges at 0MPaG.
| Assignment name | Step | Homework content | |
|
Dismantling operation ● Staff: 2 people ● Replacement personnel: 4 people ● Time required: 1 hour and 30 minutes ● Accumulated: 1 hour and 30 minutes |
1 | Rotate the nut and remove bolts ①⑯⑪⑥. | |
| 2 | Simultaneously loosen nuts ② and ⑮ 20mm. | ※Ensure that the fastening size difference at each bolt position is below 20mm, and adjust while loosening. | |
| 3 | Simultaneously loosen nuts ⑤ and ⑫ 20mm. | ||
| 4 | Simultaneously loosen nuts ③ and ⑭ 20mm. | ||
| 5 | Simultaneously loosen nuts ④ and ⑬ 20mm. | ||
| 6 | After loosening all the nuts of ② ③ ④ ⑤ ⑫⑬⑭⑮, keep the bolts of ② ⑤ ⑫⑮ and remove the bolts of ③ ④ ⑬⑭. | ||
| 7 | Simultaneously loosen nuts ② and ⑮ 20mm. | ※Ensure that the fastening size difference at each bolt position is below 20mm, and adjust while loosening. | |
| 8 | Simultaneously loosen nuts ⑤ and ⑫ 20mm. | ||
| 9 | Repeat steps 7 and 8 until all bolts are removed. | ||
| 10 | After removing all bolts, move the E-frame to the rear end of the crossbar. | ||
| ※When attaching the E-plate to the E-frame, be careful to separate it before moving it, and be careful to prevent deformation of the E-plate. | |||
|
Cleaning operation ● Staff: 3 people ● Replacement personnel: 3 people ● Required time: 6 hours ● Accumulated: 7 hours and 30 minutes |
1 | Move a heat transfer plate to the E rack side. | |
| 2 | Wash away the dirt attached to both sides of the heat transfer plate. | ||
| 3 | When the dirt cannot be completely removed by washing with water, brush it off with a brush and then rinse with water. | ||
| 4 | Move the heat transfer plate that has been cleaned of dirt to the E rack side. | ||
| 5 | Repeat steps 1-4 until all heat transfer plates have been cleaned. | ||
|
Cleaning and inspection tasks ● Staff: 2 people ● Replacement personnel: 4 people ● Required time: 2 hours ● Accumulated: 9 hours and 30 minutes |
1 | Move a heat transfer plate to the S rack side. | |
| 2 |
Check whether there is dust, algae, sand, shellfish, etc. adhering to the surface of the gasket and the groove of the heat transfer plate gasket, and whether the gasket has detached from the heat transfer plate. |
||
| 3 | If there are any debris attached, please use wiping material to remove them. If the gasket is detached, please re fix it with adhesive. | ||
| 4 | Move the cleaned heat transfer plate to the S rack side. | ||
| 5 | Repeat steps 1-4 until all heat transfer plates have been cleaned. | ||
|
Assembly operation ● Staff: 2 people ● Replacement personnel: 4 people ● Time required: 2 hours and 30 minutes ● Accumulated: 12 hours |
1 | Apply lubricating grease to all bolts. | |
| 2 | Install the bolts of ②, ⑤, ⑫and ⑮ onto the rack. | ||
| 3 | Rotate the nuts at the positions of bolts ② ⑤ ⑫⑮ to evenly adjust the locking size. | ||
| 4 | Simultaneously tighten the nut ② ⑮ 5mm. | ※Ensure that the fastening size difference at each bolt position is below 5mm, and tighten while adjusting. | |
| 5 | Simultaneously tighten the nut ⑤⑫ 5 mm. | ||
| 6 | Repeat steps 4 and 5 until fully tightened. | ||
| 7 | Install bolts ③ ④ ⑬⑭ onto the rack. | ||
| 8 | Rotate the nuts at the positions of bolts ③ ④ ⑬⑭ to evenly adjust the locking size. | ||
| 9 | Simultaneously tighten the nut ③ ⑭ 5 mm. | ※Ensure that the fastening size difference at each bolt position is below 5mm, and tighten while adjusting. | |
| 10 | Simultaneously tighten the nut ④ ⑬ 5 mm. | ||
| 11 | Repeat steps 9 and 10 until fully tightened. | ||
| 12 | Repeat steps 4-11 until the nut is tightened to the specified locking size+20mm. | ||
| 13 | Install bolts ①⑥⑪⑯ onto the frame. | ||
| 14 | Tighten nuts ① and ⑯ 5 mm simultaneously. | ※Ensure that the fastening size difference at each bolt position is below 5mm, and tighten while adjusting. | |
| 15 | Tighten nuts ⑪ and ⑥ 5 mm simultaneously. | ||
| 16 | Tighten the nuts at bolt positions ①⑥⑪⑯ to the specified locking size of+20mm. | ||
| 17 | Repeat steps 4-11 and 14, 15 until tightened to the specified locking size. | ||